PROJECT SPOTLIGHT

Garrison Dam National Fish Hatchery

GEOMEMBRANE APPLICATION: 
Fish Rearing Ponds
MATERIALS USED:
Viaflex Dura-Skrim N45B 45 mil thick Reinforced LLDPE Geomembrane Propex 801 GEOTEX Geotextile, and factory fabricated Ballast Tubes
MEMBER COMPANY: 
MEMBER COMPANIES: 
International Cover Systems (ICS) and Viaflex
PROJECT DESCRIPTION

The Garrison Dam National Fish Hatchery in North Dakota is a federal facility, which produces over 10 million native fish annually. Along with the role of providing fish for restoration stockings or balancing fish populations, the facility is also an attraction for tens of thousands of tourists annually. This project consists of lining five of their existing 66 fish rearing ponds with geosynthetics. The subgrade is a clay/sand mix which was graded, compacted, and cleared of any rocks, roots and other potential penetration hazards prior to arrival of International Cover Systems on-site to install the geosynthetics. Each of the five ponds were lined with six specifically factory fabricated panels for ease and speed of deployment. In addition, 205 factory fabricated ballast tubes ranging from 32 to 46 ft long were filled on-site with Peastone and placed on the deployed geomembrane panels after they were seamed and quality tested. The geomembrane was secured with battening to all of the associated concrete structures.

LESSONS LEARNED 

Originally, the designer for this project specified a 45mil thick reinforced polypropylene (45RPP) geomembrane due to its UV resistance in long-term exposures, high puncture resistance, tear strength, cold cracking resistance, and potable water qualities, which are compatible with fish rearing. Due to supply chain issues after the project was awarded, 45RPP geomembrane was not available for the duration of the specified project timeframe. As a result, project engineers substituted Viaflex Dura-Skrim N45 45 mil thick reinforced linear-low density polyethylene (LLDPE) geomembrane for the pond liner system. Not only was the LLDPE geomembrane available within the project timeframe scope, it also shares similar properties that originally attracted the designer to the 45RPP geomembrane.

HOW THE USE OF FABRICATION IMPROVED THIS PROJECT

The use of factory fabricated geomembranes and ballast tubes aided the project in a variety of ways. This project was originally scheduled for installation in August 2021,giving the installation crew many hours of weldable temperatures and weather. Due to the aforementioned supply chain issues of the originally specified geomembrane, the project was delayed until late October 2021. Temperatures in Riverdale, North Dakota during late October limited welding operations to only a few hours per day. As a result, it was important to minimize the amount of field geomembrane seaming, which was accomplished by factory fabricating large panels. Deploying the geotextile underlayment and large fabricated panels for the first part of the day allowed ICS to perform quality welding operations when ambient and sheet temperatures reached optimal levels. Limited field welding due to the use of large fabricated panels minimized the duration of welding each day and allowed the project to be completed with the highest quality even in late October.  

Another challenge that was mitigated by using fabricated geomembrane panels and ballast tubes is the strong North Dakota winds during late October. Ballasting was required as soon as the geomembrane panels were deployed to maintain control of the geomembrane in the windy conditions. Fabricated geomembrane panels reduced the time required to secure the geomembrane with ballast, saving valuable time, and keeping all crew members safe from what can be a dangerous situation with an unballasted geomembrane in a windy environment. All ballast tubes were factory fabricated, shipped to the site, and filled with Peastone in place.